Decentral Solution

Start-up of new installation

Preparations

The following MUST be checked BEFORE the equipment is switched on:


Water

  • The stop valve in the water supply to the pump- or main station is opened
  • The internal valves in the main station and all satellites are opened
  • The pipes connected to the cleaning system are flushed through until clean and airless water is pouring out from each satellite
  • The outlet valves in the main station and all satellites are closed
  • The filter in the water inlet to the pump- or main station is opened and cleaned

 

Compressed air

  • Air is connected

 

Power

  • Power is connected

 

Putting into operation

  • The pump- or main station is started and tested
  • The satellites are tested one by one