Start-up of new Installation
Start-up of Pump or Main station
-
Set air pressure to approx. 5 bar (Main station only)
-
Set function selector in Rinse mode (Main station only)
-
Slowly open inlet ball valve to fill pipes and pump with water
-
Open outlet to external and internal satellites to flush pipe
-
Check that water supply has sufficient volume and pressure of min. 1,5 bar
-
Check that air has sufficient volume, quality and pressure
-
Set chemical dosing
-
Check all functions (Rinse, foam and disinfection)
-
Clean filter on pump inlet after pipes have been flushed
-
Flush pipeline again through the internal satellite to take out eventual air