Satellite Station

Start-up of new installation

Start-up of Satellite station

  • Flush pipes before satellite is connected to remove impurities

  • Install satellite and connect water and air

  • Check connections to satellite

    • Water supply (pipe size, union, ball valve)

    •  Air supply (pipe size, union, ball valve)

  • Set air pressure to approx. 5 bar

  • Set function selector in Rinse mode

  • Slowly open inlet ball valve to fill pipes with water (open satellites outlets to flush pipes)

  • Set chemical dosing

  • Check all functions (Rinse, foam and disinfection)